[Pacemaker] A question and demand to a resource placement strategy function

Vladislav Bogdanov bubble at hoster-ok.com
Wed Apr 27 00:49:11 EDT 2011


Hi Yan,

27.04.2011 07:32, Yan Gao wrote:
> Hi Yuusuke,
> 
> On 04/19/11 19:55, Yan Gao wrote:
>> Actually I've been optimizing the placement-strategy lately. It will
>> sort the resource processing order according to the priorities and
>> scores of resources. That should result in ideal placement. Stay tuned.
> The improvement of the placement strategy has been committed into the
> devel branch. Please give it a test. Thanks!

Do priorities work for "utilization" strategy?

Best,
Vladislav