Hello.
I need help with pacemaker 1.1.6 and "priority".
I get cloned resource "qm", running on all nodes.
And need to run another resource, "moderate" with one condition. On a
node, that runs "moderate" resource, resource "qm" must be stopped. By
doc i can simple add "meta priority=5" to the resource definition, but
in real it does not work. I know, that i can decrease clone-max value,
but i want to get it work with priority.
Thanks.