Hi,

On Thu, Feb 10, 2011 at 02:10:00PM +0100, Johannes Freygner wrote:
> Hi,
> 
> does anybody have an idea and an example configuration for ordering the fence resource.
> 
> I have the situation and problem, meatware fencing is used before ILO fencing. So the duration to fence the through the ILO takes about 60 seconds after the meatware fencing timed out.
> Meatware should only be an emergency fence device, if ILO fencing is not working. The logs are saying meatware is used first, after timeout ILO fencing gets started.
> I tried to configure a priority attribute within the meta attributes part of the fence resource, but it's not working.

The priority attribute goes into instance attributes. That should
work.

Thanks,

Dejan

> A lot of thanks for any help,
> kind regards
> Hannes Freygner
> 
> 
> _______________________________________________
> Pacemaker mailing list: Pacemaker at oss.clusterlabs.org
> http://oss.clusterlabs.org/mailman/listinfo/pacemaker
> 
> Project Home: http://www.clusterlabs.org
> Getting started: http://www.clusterlabs.org/doc/Cluster_from_Scratch.pdf
> Bugs: http://developerbugs.linux-foundation.org/enter_bug.cgi?product=Pacemaker




More information about the Pacemaker mailing list